This profile brings together NuclearAfrica reporting and structured information on nuclear institutions, programmes, projects and peaceful nuclear applications in South Africa.
NuclearAfrica tracks nuclear policy, regulation, institutions, projects and peaceful nuclear applications in South Africa. The IAEA Outlook for Nuclear Energy in Africa places the country at Operating programme in the nuclear-power infrastructure pathway. SAFARI-1 is operational (tank-in-pool, 20 MWth) at Pelindaba. South Africa is also developing a 20–30 MW Multi-Purpose Research Reactor at Pelindaba; official 2026 project material places it in the bankability/development phase.
- Programme status
- Operating
- IAEA Milestones position
- Operating programme
- Nuclear power
- Operating
- Research reactor
- SAFARI-1 is operational (tank-in-pool, 20 MWth) at Pelindaba. South Africa is also developing a 20–30 MW Multi-Purpose Research Reactor at Pelindaba; official 2026 project material places it in the bankability/development phase.
- Pelindaba Treaty
- State Party
- Regulator
- National Nuclear Regulator
- Atomic energy institution
- Eskom
- Programme organisation
- Department of Electricity and Energy, South Africa
- Last reviewed
- October 7, 2026
Strong evidence coverage · 8/8 populated facts document-supported · 15 sources
Sources and evidence
Department of Electricity and Energy, South Africa · National official source · Primary / authoritative
National official source used as a country-level cross-check.
International Atomic Energy Agency · Official database · Primary / authoritative
PRIS is the controlling international database for operating and construction power-reactor status.
International Atomic Energy Agency · Official document / report · Primary / authoritative
IAEA continental programme-status reference. The profile stores the exact phase separately from NuclearAfrica’s simplified display status.
National / IAEA official source · National official source · Primary / authoritative
Official 2026 project profile for the proposed 20–30 MW NECSA Multi-Purpose Research Reactor at Pelindaba, recorded in the bankability phase.
National Nuclear Regulator · National official source · Primary / authoritative
National first-party institutional source. Use specific publications from this institution when a field requires a dated policy or technical claim.
International Atomic Energy Agency · Official database · Primary / authoritative
Country-specific IAEA Office of Legal Affairs factsheet.
International Atomic Energy Agency · Official database · Primary / authoritative
Country-specific IAEA Office of Legal Affairs factsheet.
International Atomic Energy Agency · Official document / report · Primary / authoritative
2026 IAEA CNPP reference for nuclear-power programme context.
International Atomic Energy Agency · Official database · Primary / authoritative
IAEA RRDB is the controlling starter reference for research-reactor information.
International Atomic Energy Agency · Official database · Primary / authoritative
IAEA RRDB is the controlling starter reference for research-reactor information.
African Commission on Nuclear Energy · Treaty / convention source · Primary / authoritative
AFCONE treaty-status reference used for the Pelindaba field.
Eskom · National official source · Primary / authoritative
National first-party institutional source. Use specific publications from this institution when a field requires a dated policy or technical claim.
South African Nuclear Energy Corporation (Necsa) · National official source · Primary / authoritative
National first-party institutional source. Use specific publications from this institution when a field requires a dated policy or technical claim.
IAEA GNSSN / FNRBA · Official database · Primary / authoritative
Regional regulatory-body directory; verify national changes against the regulator’s own website when available.
International Atomic Energy Agency · Official database · Primary / authoritative
Current IAEA Regulatory Cooperation Forum membership/context. This is supporting programme context and is not used alone to assign a Milestones phase.
Projects and programmes
PROJECT
South Africa Multi-Purpose Research Reactor
Planning- Technology
- Multi-purpose research reactor (design to be selected)
- Capacity
- 20–30 MW thermal
PROJECT
SAFARI-1 Research Reactor
Operating- Technology
- Tank-in-pool research reactor (Oak Ridge design)
- Capacity
- 20 MW thermal
PROJECT
Koeberg Nuclear Power Station
Operating- Technology
- Pressurised water reactor (PWR)
- Capacity
- 1,854 MWe net